Along the west bank of the Sacramento River, a colossal heavy-civil engineering effort is fundamentally reshaping Northern California’s flood management. The $173-million Sacramento Weir Widening Project is pushing through intensive structural phases, utilizing massive volumes of reinforced concrete and heavy machinery to extend the region’s primary flood defense line by 1,455 feet. The expansion shifts away from the historic 1916 weir’s manually operated timber gates toward a monolithic, automated passive crest. The project, in effect, is lowering the level of the Sacramento River during high-water events by reducing the height of the west bank of the river, allowing excessive floodwater to spill out of the river channel and into the Yolo Bypass.
The project is being administered by the U.S. Army Corps of Engineers, with sponsorship from the California Department of Water Resources, the California Central Valley Flood Control Board, and the Sacramento Area Flood Control Agency. Granite Construction is the general contractor.
“We’re excited to get to work on this project that will increase the safety of those living in the area. The Sacramento Weir is a vital part of our flood control infrastructure, and this upgrade will make it more effective at doing its job,” said U.S. Army Corps of Engineers Project Manager Sean McNeil.
Initial work began in 2023 with heavy earthwork for the new 2,500-foot-long North Levee setback, Old River Road embankment, and County Road 126 embankment. Concrete placements for the primary technical fish ladder wrapped up in 2024. The new, approximately 1,500-linear-foot, 25-span Old River Road vehicle bridge over the new weir is being constructed with cast-in-place piers and precast concrete girders. Presently, the crews are finishing up driving the steel-pipe piles around the redesigned north abutment. Later this year, heavy reinforced concrete work shifts into full gear across the northern bridge deck and the un-gated, fixed-crest passive weir.
The Subterranean Foundation: 100,000 Feet of Steel with Reinforcing Concrete
Before a single yard of the main weir concrete could be poured, crews had to conquer highly complex geotechnical conditions right at the groundwater line. To isolate the work zone, Granite engineered a massive dewatering system, installing a vast web of surface piping and groundwater pumps to safely evacuate water from the deep excavation pits.

One of the configurations of the 1,500 steel pipe piles driven deep into the earth, then filled with concrete.
One of the configurations of the 1,500 steel pipe piles driven deep into the earth, then filled with concrete.
With the site dry, heavy pile-driving rigs moved in to establish the project’s load-bearing foundation. Crews have driven approximately 1,500 steel pipe piles – each measuring 20 inches in diameter – deep into the earth. Totaling more than 100,000 vertical feet, these hollow steel sleeves are filled to the brim with structural concrete, anchoring both the future weir and its integrated vehicle bridge firmly into the valley floor.
Mixing the Monolith: 38,000 Cubic Yards of Concrete
The true scale of the project lies in its material demands. The expansion requires approximately 38,000 cubic yards of structural concrete. This massive volume forms the backbone of the un-gated fixed crest passive weir, designed to automatically allow overflowing river water to cascade safely over its lip into the Yolo Bypass.
To ensure the raging torrents do not erode the earth around the structure, the project integrates severe erosion barriers:
- Concrete Slope Protection: Over 130,000 square feet of poured concrete slope protection reinforces the adjacent banks.
- Tied Block Mats: Roughly 90,000 cubic yards of articulated, tied, concrete block mats line the high-velocity spillways.
- Rock Armor: More than 35,000 tons of heavy rock slope protection (riprap) pads the floor where the water loses its kinetic energy.

The multi-tiered concrete geometry of the fish passage structure takes shape, serving as a dual-purpose migratory ladder for threatened local aquatic species.
Engineering Through Structural Adjustments
Working with such immense concrete weight on soft river basin soils presents distinct structural challenges. In late 2025, sensors detected a case of differential settlement, revealing that the earth beneath the newly poured north abutment wall had shifted unevenly.
To rectify the settlement without risking long-term structural integrity, engineers adjusted the design, deploying specialized rigs to wrap up additional targeted pile-driving directly around the affected bridge support. While this corrective phase has pushed final site cleanup into 2027, reinforced concrete work is actively advancing. Crews are moving methodically to complete the northern vehicle bridge deck so local traffic can finally shift permanently off the levee walls.
Final site demobilization, structural cleanup, and extensive erosion-control planting across the widened bypass channels will wrap up the project work in November 2027.
U.S. Army Corps of Engineers Project Manager Sean McNeil is joined by USACE Resident Engineer and Administrative Contracting Officer Zachary Moore.
The Granite Team includes Project Manager Kelly Curtis, Assistant Project Manager Pete Cavallini, Construction Quality Control Manager Mike Schaffner, Lead Bridge Project Engineer Christian Mercik, Lead Weir Project Engineer Brent Zoucha, Structures Superintendent William Dellapenna, Earthwork Superintendent Brian Murphy, and Site Safety & Health Officer Gabe Martinez.


